| Paper | Title | Page | 
    
        | TU3I01 | Commissioning of the LCLS-II Machine Protection System for MHz CW Beams | 154 | 
    
        |  | 
                J.A. Mock, A.S. Fisher, R.T. Herbst, P. Krejcik, L. SapozhnikovSLAC, Menlo Park, California, USA
 |  | 
    
        |  | Beam power at the LCLS-II linac and FEL can be as high as several hundered kW with CW beam rates up to 1 MHz. The new MPS has a latency of less than 100 µs to prevent damage when a fault or beam loss is detected. The MPS architecture encompasses the multiple FEL beamlines served by the SC linac and can mitigate a fault in one beamline without impacting the beam rate in a neighboring beamline. The MPS receives inputs from various devices including loss monitors and charge monitors as well as magnet power supplies and BPMs to pre-emptively turn of the beam if a fault condition is detected. Link nodes distributed around the facility gather the input data and stream it back to a central processor that signals other link nodes connected to beam rate control devices. Commmissioning and experience with the new system will be described. |  | 
    
        |   | Slides TU3I01 [4.239 MB] |  | 
    
    	  | DOI • | reference for this paper 
              ※ doi:10.18429/JACoW-IBIC2023-TU3I01 |  | 
    
    	  | About • | Received ※ 06 September 2023 — Revised ※ 08 September 2023 — Accepted ※ 12 September 2023 — Issue date ※ 25 September 2023 | 
    
    	  | Cite • | reference for this paper using 
              ※ BibTeX, 
              ※ LaTeX, 
              ※ Text/Word, 
              ※ RIS, 
              ※ EndNote (xml) |  | 
    
        |  |